Green power transmission development in India
Over 50GW of renewable capacity is stranded due to transmission constraints as of June 2025.

Date of release: September 2025
Report by JMK Research and IEEFA
Indiaโs power transmission network, one of the largest in the world, spans over 494,000 circuit kilometres (ckm) of lines and 1.33 million megavolt-amperes of transformation capacity, forming a fully synchronised national grid. However, the network struggles to keep up with renewable energy deployment, leading to a growing gap between clean power generation and the availability of evacuation infrastructure. This imbalance limits renewable integration and increases the risk of stranded assets and higher delivery costs.
The widening gap between planned and actual transmission network expansion is becoming evident. In FY2025, only 8,830ckm of new transmission lines were commissioned against a target of 15,253ckm, reflecting a 42% shortfall, with Inter-State Transmission System (ISTS) additions at their lowest in a decade. Alongside this capacity gap, system inefficiencies are emerging, with analysis by the National Renewable Energy Laboratory indicating that up to 71% of ISTS corridors operate below 30% utilisation, underscoring the mismatch between infrastructure availability and actual power flows.
Market distortions further aggravate the situation. In several high-demand corridors, speculative hoarding of transmission capacity by entities without genuine project intent has driven up connectivity prices and delayed access for viable projects. Structural and procedural bottlenecks, including right-of-way (RoW) disputes, prolonged land acquisition processes, restrictions on equipment procurement, and multi-agency approval requirements, add to the delay. Among these, RoW remains one of the most significant barriers to timely transmission development. Similar land acquisition hurdles in the US have also slowed new transmission build-outs.
In India, the impact is most visible in Rajasthan, where 8 gigawatts (GW) of renewable energy capacity remains stranded, with nearly half curtailed during peak solar hours. Delayed completion of the Associated Transmission Systemโthe dedicated transmission infrastructure linked to new generation projectsโalong with capacity hoarding and ecological directives mandating underground cabling in Great Indian Bustard habitats, have compounded evacuation challenges, inflated project costs, and reduced operational efficiency.
The implications are significantโover 50GW of renewable energy capacity is currently stranded nationwide, increasing per-unit transmission costs, weakening project viability, and deterring private investment. These constraints limit the pace at which new capacity can be brought online and undermine Indiaโs ability to integrate variable renewable energy at scale, risking missed milestones in the countryโs clean energy transition.
A unified generation-transmission planning framework that aligns timelines and locations for both generation and transmission capacity additions is essential. A single-window clearance system with strict timelines should be implemented to streamline land, RoW, and connectivity approvals. Performance-based incentives and disincentives tied to asset utilisation metrics can encourage timely commissioning and sustained operations. Scaling asset monetisation and public-private partnerships will be essential to unlocking capital for both inter-state and intra-state projects. In parallel, reconductoring of congested corridors and integration of energy storage systems should be prioritised in renewable-rich regions to enhance capacity utilisation and reduce curtailment.
A coordinated approachโcombining regulatory reform, operational efficiency measures, and capital mobilisationโwill be critical to transforming Indiaโs transmission network into a flexible, resilient system capable of supporting high renewable penetration while ensuring cost-effective and reliable power delivery. The recent extension of ISTS charge waivers for storage and the implementation of time block-based General Network Access allocationโwhich allows power generators to use the transmission network without pre-identifying buyersโare steps in the right direction. Without targeted reforms, misalignment between generation commissioning and evacuation infrastructure is likely to continue driving congestion, curtailment, and systemic inefficiencies, ultimately slowing progress towards achieving Indiaโs decarbonisation objectives.
Table of Contents
- Key Findings
- Executive Summary
- Indiaโs power transmission network at a glance
- Government initiatives for green power transmission development
- Transmission development challenges
- Underutilisation of transmission infrastructure
- Impact on the renewable energy sector
- Recommendations
- Conclusion
Enter the E-mail ID to download the report
